Clearwater cuts $9 million from Think about Clearwater waterfront park construction

donny

CLEARWATER — Two months right after the City Council paused a $6.4 million renovation of the downtown Major Library, the city is moving this 7 days to scrap the up grade altogether. The first conclusion to incorporate a makeover of the library into the Visualize Clearwater strategy, a roughly $64 […]

CLEARWATER — Two months right after the City Council paused a $6.4 million renovation of the downtown Major Library, the city is moving this 7 days to scrap the up grade altogether.

The first conclusion to incorporate a makeover of the library into the Visualize Clearwater strategy, a roughly $64 million redevelopment of the downtown waterfront, was produced by the town council in June 2019. But considering the fact that then, the make-up of the 5-member council has changed, with a few new officers elected in March.

Price estimates for the library also fluctuated, even following council members voted this yr to nix a fifth-floor element, prompting them to put the renovation on maintain on Oct. 1.

“I think anyone started asking inquiries about what was the actual price tag reward of undertaking the improvements to the library, and the conclusion was: not more than enough,” mentioned Mayor Frank Hibbard, who was elected in March together with council members Kathleen Beckman and Mark Bunker.

The city is now on track to slash $9 million of building expenditures from the downtown waterfront challenge by nixing the library renovation and scaling again some cosmetic elements inside of the park. The alterations would drop the working building estimate of Picture Clearwater from $64 million to $55 million, assistant town supervisor Michael Delk stated at a get the job done session on Monday.

But the updated $55 million figure does not include $10 million the metropolis has already used on structure and utility perform to day.

“It’s nevertheless a $64 million park,” engineering design manager Tim Kurtz verified right after council member Kathleen Beckman pointed out the discrepancy.

The now-rescinded renovation of the 16-calendar year-previous library experienced provided a reconfiguration of the principal entry, a new grand staircase, a new artwork gallery, redesigned very first ground/circulation space, renovated workspaces and a new city council chambers.

The council closed the library to the public on Sept. 25 in get to start out renovations. It remained closed just after the council paused the task Oct. 1.

Key Library personnel and equipment experienced been relocated all through the closing. With the renovations now scrapped, Library Director Jennifer Obermaier mentioned the Main Library will reopen to the community “as quickly as achievable,” with a goal day of Dec. 14.

Delk stated the town has used involving $300,000 and $400,000 on style and allow get the job done on the library renovation that will now not be utilised.

Other price tag cuts designed to Visualize Clearwater incorporate scaling again the enjoy region next to the lake, removing the south bluff wander, removing a pedestrian bridge over Cleveland Avenue, eliminating comprehensive plantings from the yard, and other generally cosmetic adjustments, in accordance to Kurtz, the engineering manager.

On Thursday, the council will have to formally vote on whether to eliminate the library renovation from Think about Clearwater. Delk mentioned the consensus will give the city’s specialist, Stantec, the potential to collect remaining pricing with contractors and achieve ultimate permits in excess of the up coming 90 times.

Delk expects park development to start out in March or April, even though Duke Strength has already started underground utility operate within just the 22-acre footprint. He said the council will see a ultimate confirmed expense estimate, from Stantec, confirming contractor pricing ahead of design.

The target completion day of the park is Tumble 2023.

The metropolis has recognized $49.7 million to pay for building, generally coming from Penny for Pinellas 1-cent income tax revenue, town tax profits and up to $30 million of bond proceeds.

Council customers also hope to acquire earnings by advertising the naming rights of the park’s 4,000-covered seat amphitheater and other corporate sponsorships.

The city is also establishing a ask for for proposals for a few city-owned parcels bordering the park for builders to develop retail, residential and lodge progress. Final yr, the town approximated it could make $23 million from the sale of those people sites: the previous metropolis hall residence, an adjacent 1.4 acre ton on Pierce Street and the vacant corner of Osceola Avenue and Cleveland Road, which previously housed the Harborview Centre. The lease or sale of the City Corridor and Harborview sites would require voter approval.

Next Post

The US is averaging just one COVID-19 death per minute, according to a global heath skilled

© John Lamparski/NurPhoto/Getty Visuals Medical workers go a patient on a gurney across the skyway at Mt. Sinai Morningside Healthcare facility on May possibly 18, 2020 in New York City. John Lamparski/NurPhoto/Getty Pictures The US is averaging one particular loss of life from COVID-19 per moment, Dr. Beth Bell, a […]

Subscribe US Now